Gatwick Diamond Development

Project Info

  • Project Value

    £358,000

  • Category

    Paving

Job Title

Gatwick Diamond Development, Manor Royal Crawley

Client

Willmott Dixon

Description

Willmott Dixon appointed as the main contractor to develop a large parcel of land on the Manor Royal Industrial Estate for the building of a prestigious office block appointed appointed us as the specialist block laying contractor to supply and lay 7500m2 Marshall Priora porous block paving to the car park and access roads together with 1420m2 400×400 St George slab paving tp the footways.

Parking bays were laid in buff with delineation in white, access roads in charcoal all laid in 90° herringbone pattern on porous macadam base.

Our staff worked in 3 and 4 man teams to complete laying and cutting operations in a phased programme maintaining access for Willmott’s building and trades subcontractors to continue work on the office build throughout.

Duration

20 Weeks